Linac Coherent
Light Source Project
Submitted by Nur Kasdi, Johnson
Western Gunite Company, San Leandro, CA.
Job Date:
November 2006 to December 2007

|
LOCATION |
Menlo Park, California
|
Click on
each thumbnail to enlarge picture.


 |
|
OWNER & CONTACT |
Stanford Linear Accelerator Center
|
|
MANAGER/ENGINEER |
Jacobs & Associates |
|
GENERAL CONTRACTOR |
Turner Construction & Affholder, Inc.
|
|
CONTRACT AMOUNT |
$2,200,000.00
|
|
SCOPE OF WORK
|
The Linac Coherent Light Source Project involved
the a new extension of an existing linear
accelerator near Stanford University. The work
included the installation of final shotcrete
lining inside the Undulator Tunnel, X-Ray
Tunnel, Access Tunnel, and Far Experimental
Hall. All major contract items of the project
were completed in house. |
|
DATES |
Start Date: August 2007
Completion Date: April 2008 |
|
CONTRACT QUANTITIES
|
1. Installation
of 1,750 lineal feet of shotcrete tunnel lining
with wire mesh and steel reinforcement.
2. Approximately
1,850+ cubic yards of shotcrete. |
|
SAFETY RECORD
|
During the course of this project, our firm
managed to maintain a safety record of “0”
serious incidents or lost time incidents. |
|
CONTACTS |
Larry Totten:
larry_totten@jwgunite.com
Nur Kasdi:
nurk@jwgunite.com |
|
LINKS |
LCLS Construction
Status
Panoramic Views for
Far Experimental Hall
LCLS Brochure |
|
Click
the
here to
return.
 |